At a glance
Infrastructure investment : S$140 million
Type of system : Straddle-type monorail on
concrete beams
Driver-operated, fully computerized
Direction : Elevated 2-way track
No. of trains: : Four trains with two cars per
train
Train dimensions: : 23.4m (L) x 2.75m (W) x 3.33m
(H)
Train capacity: : 174 people per train
Seating/standing ratio: : 30:144
System capacity: : 3,000 people/hour/direction
expandable to 4,000 people/hour/direction
Number of train stations : 4
Total route length: : 2.15km (one way)
Total track length : 4.30km
Expected waiting time: : 3 minutes
Expected journey time: : 6 minutes (one way from
HarbourFront Station to Palawan Beach Station)
Average train speed: : 30 km/h
Operational date : Year 2006